Integrated lot sizing and production scheduling formulations: an application in a refractory cement industry

Abstract

This work presents an integrated lot sizing and scheduling problem for a large refractory cement manufacturer. Three mathematical formulations were addressed: two already presented in the literature, and one proposed as an alternative to the existing ones. This study aims to compare these formulations with respect to their performance and applicability as a decision support tool. One of these formulations uses continuous variables, whereas the others are based on time-indexed variables. These mathematical models address the specific concept of how variables and parameters are defined, requiring assumptions and particular settings to suit the real problem. In order to consider the different aspects of the practical situation, several instances were generated from uniform distributions based on real information. Extensive computational tests were run and, based on the results, the formulations were evaluated as a decision support tool and their efficiencies were compared.

Keywords:
Scheduling; Lot sizing; Production planning and control; Mathematical programming formulations

Resumo

O presente trabalho apresenta um problema de dimensionamento e sequenciamento integrados para uma fábrica de grande porte de cimento para refratário. Foram abordadas três formulações matemáticas: duas presentes na literatura e uma proposta como alternativa às já existentes. Este estudo tem como objetivo comparar as formulações tanto em relação ao seu desempenho quanto à sua aplicabilidade como ferramenta de suporte à tomada de decisão. Uma dessas formulações utiliza variáveis contínuas e as outras são baseadas em variáveis indexadas no tempo. Estes modelos matemáticos abordam um conceito específico de como as variáveis e parâmetros são definidos, exigindo premissas e definições particulares para se adequar ao problema real. A fim de considerar os diferentes aspectos da situação prática, foram geradas várias instâncias a partir de distribuições uniformes, baseadas em informações reais. Extensivos testes computacionais foram executados e, com base nesses resultados, as modelagens foram avaliadas como ferramenta de apoio à decisão e as suas eficiências foram comparadas.

Palavras-chave:
Scheduling; Lot sizing; Planejamento e controle da produção; Modelos de programação matemática

1 Introduction

Data from the Brazilian Ministry of Mines and Energy (Brasil, 2009Brasil. Ministério de Minas e Energia – MME. (2009). Recuperado em 15 de maio de 2014, de http://www.mme.gov.br/mme
http://www.mme.gov.br/mme...
) state that the refractory represents a segment of extreme importance, since all industrial processes that use heat directly require them, especially basic industries, as steel mills. According to the Magnesita Refratários (2015)Magnesita Refratários. (2015). Soluções refratárias. Recuperado em 23 de fevereiro de 2015, de http://ri.magnesita.com
http://ri.magnesita.com...
, the market of these products handles about US$ 25 billion per year all over the world, with the top six companies representing nearly 40% of all global refractories sales. It is predicted that consumption of these products increases 3.3% until the year 2028.

This work emerged from the need to seek advantages in leverage of financial results, considering a market with increasing competition and with close price values. Thus, a greater organization of the production line is essential for the cost reduction without interfering on the quality of the final product. The Operational Research comes as a tool to enable improvements in order to obtain a better organization of the production process, allowing a support to the decision making by mathematical modeling of real situations (Nogueira, 2008Nogueira, T. H. (2008). Modelagem do sequenciamento da ensilagem em processos industriais de formação de receitas (Dissertação de mestrado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte.).

This study is the result of a real problem of lot sizing and production scheduling in a large refractory cement industry which is located in Contagem/MG. This company dedicates in mining, producing and marketing a wide line of refractory materials, being the third largest producer in the world and leader in the Brazilian market of these products. It currently employs about 6,400 employees and has production capacity of over 1.4 million of tones of refractories per year, achieving a sales revenue of 2.7 billion of reais in 2013, with selling to more than 1,000 customers in over 100 countries, resulting in an approximated net profit of 30 million.

The objective of this study is to minimize the cost of inventory and unmet demand, usually caused by the lack of organization of the factory and its activities. The studied process is performed in continuous flow and it can be characterized as a single machine problem which receives raw material and executes the process, resulting in a final product. In this process, the bottleneck machine is responsible for the production rate and asymmetrical setup times between production lots are considered, i.e., they have time variations for each type of product/product family.

In this paper the problem is mathematically formulated in three distinct ways, two which already exists on the literature and a new one. In order to compare the performance of the three formulations, the lower bounds, obtained by means of the LP (linear programming) relaxation, and the found optimum solution, when using commercial software, were discussed. Since the broached problem is NP-Hard, with larger instances the computational time is a limit for the software in achieving the optimal solution. The LP relaxation was used for these formulations in order to meet the lower bounds, relaxing all their integer variables.

With the purpose of evaluating the proposed formulation, it was made a study comparing it with the other two approaches: a formulation with continuous variables based on Manne (1960)Manne, A. S. (1960). On the job-shop scheduling problem. Operations Research, 8(2), 219-223. http://dx.doi.org/10.1287/opre.8.2.219.
http://dx.doi.org/10.1287/opre.8.2.219...
, Santos (2006)Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte. and Carvalho & Santos (2006)Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO., and a reference formulation with time-indexed variables based on Toledo et al. (2007)Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009.
http://dx.doi.org/10.1590/S0101-74382007...
, Toso et al. (2009)Toso, E. A., Morabito, R., & Clark, A. R. (2009). Lot sizing and sequencing optimization at an animal-feed plant. Computers & Industrial Engineering, 57(3), 813-821. http://dx.doi.org/10.1016/j.cie.2009.02.011.
http://dx.doi.org/10.1016/j.cie.2009.02....
and Ferreira et al. (2010)Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007.
http://dx.doi.org/10.1016/j.cor.2009.06....
. These formulations are applied to instances taken from real data and the results are compared.

To achieve the objectives described herein it was used the rolling horizon approach, as shown in Figure 1. This technique consists in a differential to reduce computational time, where the first period is divided into sub-periods and it will slide in time as planning is performed, with the scheduling detailed only for the immediate period. After, the horizon is rolled and the formulation is executed again, being updated with new information. The planning for future periods is done only for evaluation of the capacity. Thus, the number of variables in the formulation is drastically reduced (Carvalho & Santos, 2006Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO.).

Figure 1
Rolling horizon.

Buxey (1989)Buxey, G. (1989). Production scheduling: practice and theory. European Journal of Operational Research, 39(1), 17-31. http://dx.doi.org/10.1016/0377-2217(89)90349-4.
http://dx.doi.org/10.1016/0377-2217(89)9...
highlights the uselessness in spending efforts with long periods, since that the uncertainty grows with the size of the auscultated time. The proposed planning formulation uses the planning horizon as discussed in Santos (2006)Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte..

This work is divided into six sections: section 1 gives an introduction to the broached subject. In section 2 it is done a literature discussion about this theme. The section 3 discusses the type of problem and the company's particularities under study. The section 4 presents the proposed formulation and other ones existing on the literature, comparing them. In section 5 the results of the presented formulations are discussed. Finally, the section 6 is about the conclusions of the study.

2 Literature review

Studies about production planning are found in large quantity in the literature. According to Fernandes & Santoro (2005)Fernandes, F. C. F., & Santoro, M. C. (2005). Avaliação do grau de prioridade e do foco do planejamento e controle da produção (PCP): modelos e estudos de casos. Gestão & Produção, 12(1), 25-38. http://dx.doi.org/10.1590/S0104-530X2005000100004.
http://dx.doi.org/10.1590/S0104-530X2005...
Production Planning and Control (PPC) problems are broached in three ways: considering only the production lot sizing, considering only the daily scheduling of items to be produced or considering these two aspects in an integrated way, i.e., the PPC integrated with scheduling. The latter form tries to join the long term planning to the short term one, making a weekly lot sizing of the items and daily scheduling of them.

The Table 1 shows in chronological order the main references in the literature used for this study. As it can be observed, about 10% of these works discuss the lot sizing problem. All of them have the objective of minimizing costs and one study uses for this the Lagrangian Relaxation.

Table 1
The used published works as well as its resolution method and objective.

Approximately 30% of the studies presented in the Table 1 are about the production scheduling problems. Considering the ones which present mathematical models, almost 70% of them use exact methods, such as Branch and Bound, and 30% heuristics. More than 40% of the scheduling problems aim to reduce the anticipation and delay costs, and the remaining 60% have various goals, such as minimizing the costs of the production resources and the production line setup.

Around 60% of the analyzed works discuss about the integrated PPC and scheduling problems. Considering the studies that have mathematical models, 40% of them use to solve the exact methods, such as Branch and Bound and Branch and Cut, 50% use relax-and-fix heuristic and the rest use Local Search algorithms and other heuristics. Concerning to the objectives of these studies, 45% of them minimize together the costs of inventory, unmet demand/backward and setup. The others have diverse objectives, including minimization of the extra hours and production costs. Around 80% of the works can be considered as a multi objective problem, and of these, 74% are integrated problems, 10% are lot sizing problems and 16% are scheduling problems.

It is possible to notice that, as the present study, almost 90% of the works aim to minimize the costs, as the stock, unmet demand, production, delay or preparation costs. The problem under study is not found with the same focus on practical applications in the literature. Those with greater compatibility were found in the works of Toso & Morabito (2005)Toso, E. A. V., & Morabito, R. (2005). Otimização no dimensionamento e sequenciamento de lotes de produção: estudo de caso numa fábrica de rações. Gestão & Produção, 12(2), 203-217. http://dx.doi.org/10.1590/S0104-530X2005000200006.
http://dx.doi.org/10.1590/S0104-530X2005...
and Henriques et al. (2010)Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO., which analyze scheduling problems of discrete production lines, focusing on the attendance of the final products and determining the lot sizing. Other studies that are similar in relation to the objectives of this work are Araujo et al. (2007)Araujo, S. A., Arenales, M. N., & Clark, A. R. (2007). Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups. Journal of Heuristics, 13(4), 337-358. http://dx.doi.org/10.1007/s10732-007-9011-9.
http://dx.doi.org/10.1007/s10732-007-901...
, Ferreira et al. (2009)Ferreira, D., Morabito, R., & Rangel, S. (2009). Solution approaches for the soft drink integrated production lot sizing and scheduling problem. European Journal of Operational Research, 196(2), 697-706. http://dx.doi.org/10.1016/j.ejor.2008.03.035.
http://dx.doi.org/10.1016/j.ejor.2008.03...
, Ferreira et al. (2010)Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007.
http://dx.doi.org/10.1016/j.cor.2009.06....
and Stadtler & Sahling (2012)Stadtler, H., & Sahling, F. (2012). A lot-sizing and scheduling model for multi-stage flow lines with zero lead times. European Journal of Operational Research, 225(3), 404-419. http://dx.doi.org/10.1016/j.ejor.2012.10.011.
http://dx.doi.org/10.1016/j.ejor.2012.10...
.

The scheduling problems are widely studied in the literature due to the difficulty level and applicability, and they may extend to production scheduling, projects, vehicle routing, among others (Nogueira, 2014Nogueira, T. H. (2014). Single machine scheduling problems with sequence dependent setup times (Tese de doutorado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte.). The mathematical models of scheduling consist of allocating tasks and scarce resources to the products in order to meet the pre-established goal, setting the sequence of goods production, as discussed in Allahverdi et al. (2008)Allahverdi, A., Ng, C. T., Cheng, T. C. E., & Kovalyov, M. Y. (2008). A survey of scheduling problems with setup times or costs. European Journal of Operational Research, 187(3), 985-1032. http://dx.doi.org/10.1016/j.ejor.2006.06.060.
http://dx.doi.org/10.1016/j.ejor.2006.06...
, Pinedo (2012)Pinedo, M. L. (2012). Scheduling: theory, algorithms, and systems. 4 ed. Nova York: Springer. and Leung (2004)Leung, J. Y.-T. (2004). Handbook of scheduling: algorithms, models, and performance analysis. Boca Raton: Chapman & Hall /CRC. 1224 p.. Applications of these problems are also seen in Lawler (1976)Lawler, E. L. (1976). Combinatorial optimization: networks and matroids. New York: Holt, R. & Winston. 362 p., Manne (1960)Manne, A. S. (1960). On the job-shop scheduling problem. Operations Research, 8(2), 219-223. http://dx.doi.org/10.1287/opre.8.2.219.
http://dx.doi.org/10.1287/opre.8.2.219...
, Du & Leung (1990)Du, J., & Leung, J. Y. T. (1990). Minimizing total tardiness on one machine is NP-hard. Mathematics of Operations Research, 15(3), 483-495. http://dx.doi.org/10.1287/moor.15.3.483.
http://dx.doi.org/10.1287/moor.15.3.483...
, Sousa & Wolsey (1992)Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059.
http://dx.doi.org/10.1007/BF01586059...
, Tavares (2002)Tavares, L. V. (2002). A review of the contribution of operational research of project management. European Journal of Operational Research, 136(1), 1-18. http://dx.doi.org/10.1016/S0377-2217(01)00097-2.
http://dx.doi.org/10.1016/S0377-2217(01)...
, Santos & Massago (2007)Santos, M. O., & Massago, S. (2007). Um método heurístico para o problema de dimensionamento e sequenciamento de lotes com custos e tempo das preparações sequencia- dependentes. Anais do 39º Simpósio Brasileiro de Pesquisa Operacional. Fortaleza: SBPO., Bustamante (2007)Bustamante, L. (2007). Minimização do custo de antecipação e atraso para o problema de sequenciamento de uma máquina com tempo de preparação dependente da sequência: aplicação em uma usina siderúrgica (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte., Yamashita & Morabito (2007)Yamashita, D. S., & Morabito, R. (2007). Um algoritmo exato para o problema de programação de projetos com custo de disponibilidade de recursos e múltiplos modos. Pesquisa Operacional, 27(1), 27-49., Chen & Askin (2009)Chen, J., & Askin, R. G. (2009). Project selection, scheduling and resource allocation with time dependent returns. European Journal of Operational Research, 193(1), 23-34. http://dx.doi.org/10.1016/j.ejor.2007.10.040.
http://dx.doi.org/10.1016/j.ejor.2007.10...
, Ramos & Oliveira (2011)Ramos, R. S., & Oliveira, F. B. (2011). Uma abordagem ao problema de sequenciamento em uma máquina com penalidades por antecipação e atraso da produção por meio de algoritmos evolutivos. Conexão Ciência, 6(2), 21-37. and Rego (2013)Rego, M. F. (2013). Algoritmos multiobjetivos para o problema de sequenciamento de tarefas em uma máquina com tempo de preparação dependente da sequência e da família (Dissertação de mestrado). Universidade Federal de Ouro Preto, Ouro Preto..

The lot sizing decisions are related to the amount of end items. They should consider the influence of production factors, the costs related to the latters and how these costs can influence the PPC. The works that address only the lot sizing problem can be seen in Brahimi et al. (2006)Brahimi, N., Dauzere-Peres, S., Najid, N. M., & Nordli, A. (2006). Single item lot sizing problems. European Journal of Operational Research, 168(1), 1-16. http://dx.doi.org/10.1016/j.ejor.2004.01.054.
http://dx.doi.org/10.1016/j.ejor.2004.01...
and Molina et al. (2013)Molina, F., Morabito, R., & Araujo, S. A. (2013). Modelos matemáticos para problemas de dimensionamento de lotes com restrições de capacidade e custos de transporte. Gestão & Produção, 20(3), 573-586. http://dx.doi.org/10.1590/S0104-530X2013000300006.
http://dx.doi.org/10.1590/S0104-530X2013...
.

The studied problem is composed of an integrated lot sizing and scheduling formulation, as discussed in studies by Araujo et al. (2004)Araujo, S. A., Arenales, M. N., & Clark, A. R. (2004). Dimensionamento de lotes e programação do forno numa fundição de pequeno porte. Gestão & Produção, 11(2), 165-176. http://dx.doi.org/10.1590/S0104-530X2004000200003.
http://dx.doi.org/10.1590/S0104-530X2004...
, Carvalho & Santos (2006)Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO., Santos (2006)Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte., Toledo et al. (2007)Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009.
http://dx.doi.org/10.1590/S0101-74382007...
, Araujo et al. (2007)Araujo, S. A., Arenales, M. N., & Clark, A. R. (2007). Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups. Journal of Heuristics, 13(4), 337-358. http://dx.doi.org/10.1007/s10732-007-9011-9.
http://dx.doi.org/10.1007/s10732-007-901...
, Toso et al. (2009)Toso, E. A., Morabito, R., & Clark, A. R. (2009). Lot sizing and sequencing optimization at an animal-feed plant. Computers & Industrial Engineering, 57(3), 813-821. http://dx.doi.org/10.1016/j.cie.2009.02.011.
http://dx.doi.org/10.1016/j.cie.2009.02....
, Ferreira et al. (2009)Ferreira, D., Morabito, R., & Rangel, S. (2009). Solution approaches for the soft drink integrated production lot sizing and scheduling problem. European Journal of Operational Research, 196(2), 697-706. http://dx.doi.org/10.1016/j.ejor.2008.03.035.
http://dx.doi.org/10.1016/j.ejor.2008.03...
, Ferreira et al. (2010)Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007.
http://dx.doi.org/10.1016/j.cor.2009.06....
, Bernardes et al. (2010)Bernardes, E. D., Araujo, S. A., & Rangel, S. (2010). Reformulação para um problema integrado de dimensionamento e sequenciamento de lotes. Pesquisa Operacional, 30(3), 637-655., Henriques et al. (2010)Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO., Stadtler (2010)Stadtler, H. (2010). Multi-level single machine lot-sizing and scheduling with zero lead times. European Journal of Operational Research, 209(3), 241-252. http://dx.doi.org/10.1016/j.ejor.2010.09.022.
http://dx.doi.org/10.1016/j.ejor.2010.09...
, Shim et al. (2011)Shim, I.-S., Kim, H.-C., Doh, H.-H., & Lee, D.-H. (2011). A two-stage heuristic for single machine capacitated lot-sizing and scheduling with sequence-dependent setup costs. Computers & Industrial Engineering, 61(4), 920-929. http://dx.doi.org/10.1016/j.cie.2011.06.002.
http://dx.doi.org/10.1016/j.cie.2011.06....
, Defalque et al. (2011)Defalque, C. M., Rangel, S., & Ferreira, D. (2011). Usando o ATSP na modelagem do problema integrado de produção de bebidas. TEMA. Tendências em Matemática Aplicada e Computacional, 12(3), 195-209. http://dx.doi.org/10.5540/tema.2011.012.03.0195.
http://dx.doi.org/10.5540/tema.2011.012....
, Clark et al. (2011)Clark, G. E. A., Almada-Lobo, B., & Almeder, C. (2011). Lot sizing and scheduling: industrial extensions and research opportunities. International Journal of Production Research, 49(9), 2457-2461. http://dx.doi.org/10.1080/00207543.2010.532908.
http://dx.doi.org/10.1080/00207543.2010....
, Stadtler & Sahling (2012)Stadtler, H., & Sahling, F. (2012). A lot-sizing and scheduling model for multi-stage flow lines with zero lead times. European Journal of Operational Research, 225(3), 404-419. http://dx.doi.org/10.1016/j.ejor.2012.10.011.
http://dx.doi.org/10.1016/j.ejor.2012.10...
and Seeanner & Meyr (2013)Seeanner, F., & Meyr, H. (2013). Multi-stage simultaneous lot-sizing and scheduling for flow line production. OR-Spektrum, 35(1), 33-73. http://dx.doi.org/10.1007/s00291-012-0296-1.
http://dx.doi.org/10.1007/s00291-012-029...
.

The studies that use heuristics to address integrated formulations can be seen in Araujo et al. (2007)Araujo, S. A., Arenales, M. N., & Clark, A. R. (2007). Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups. Journal of Heuristics, 13(4), 337-358. http://dx.doi.org/10.1007/s10732-007-9011-9.
http://dx.doi.org/10.1007/s10732-007-901...
and Shim et al. (2011)Shim, I.-S., Kim, H.-C., Doh, H.-H., & Lee, D.-H. (2011). A two-stage heuristic for single machine capacitated lot-sizing and scheduling with sequence-dependent setup costs. Computers & Industrial Engineering, 61(4), 920-929. http://dx.doi.org/10.1016/j.cie.2011.06.002.
http://dx.doi.org/10.1016/j.cie.2011.06....
. The exact methods are also used to solve integrated problems, as it can be seen in Toledo et al. (2007)Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009.
http://dx.doi.org/10.1590/S0101-74382007...
. More detailed reviews on the exact methods can be seen in Nemhauser & Wolsey (1988)Nemhauser, G. L., & Wolsey, L. A. (1988). Integer and combinatorial optimization. New York: Wiley., Pochet & Wolsey (2006)Pochet, Y., & Wolsey, L. A. (2006). Production planning by mixed integer programming (Springer Series in Operations Research and Financial Engineering). Nova York: Springer. 499 p., Arenales et al. (2007)Arenales, M., Armentano, V. A., Morabito, R., & Yanasse, H. H. (2007). Pesquisa operacional. 6 ed. Rio de Janeiro: Elsevier. 524 p. and Wolsey (2008)Wolsey, L. A. (2008). Mixed integer programming. In W. W. Benjamin (Ed.). Wiley Encyclopedia of Computer Science and Engineering (pp. 1-10). New York: John Wiley & Sons, Inc..

3 Problem

This study consists of an integrated lot sizing and scheduling problem with multi item, single machine, capacitated and the possibility of making stock and not meeting the demand. The database for the study was collected in a large refractory cement industry located in Contagem, Minas Gerais.

The details of the production process have greater emphasis on operational and organizational issues of the factory and by an analysis of them it is intended to find inconsistencies that might bring losses for the organization in terms of efficiency. This process has a linear flow and it can be treated as a single machine problem, with the phase of lower production rate determining the process speed. It starts at the receiving raw materials step and ends with the shipment of the final product to the customer.

The factory works in two turns of production and it has 32 silos available for input storage, of which 11 silos store raw materials that are common for many products and the other silos exchanged their types of raw materials according to the production requirements. The receiving is done with bags that are maintained in bins that are near to the production line entrance, which are supplied weekly (Figure 2 in section A).

Figure 2
The disposition of the studied process.

The silos, Figure 2 in section B, are emptied after the production order and supplied with the necessary raw materials. The setup time for the product manufacturing is about 50 minutes, with 30 minutes for the silo unloading and 20 minutes for supplying it. There is preparation of one raw material at time, since there is a single device which transports the raw material to the silos. The bags with these materials are transported to the silos entrance and carried by an elevator to the empty silos, where the inputs are ensiled. Each silo has 2,000 kg of capacity. After filling these, the raw material is weighed by the hopper in the necessary amount for the receipt formation in the transport carriage, Figure 2 in section C. The silos are located over a trolley which receives the raw material after weighed and directs them to the mixer, Figure 2 in Section D, for subsequent bagging. The Figure 2 illustrates the production process of the studied company, following the flow: bin, ensilage, receipt formation and mixer.

The ensilage has a great impact on idle time, since, as previously described, it spends about 50 minutes in each silo. The swap of product/product family may result in changing raw materials in many silos, therefore, the greater the amount of silos that requires change, greater the idle time. Furthermore, product/product family which may cause contamination increases the setup time, because of the requirement for additional cleaning. Thus, the ensilage is crucial for the scheduling due its influence on idle time and available capacity. It is noteworthy that the discussed data were strictly generated to consider the reality described here.

This study aims to create a greater integration between the tactical and operational decision making levels, seeking to facilitate the activities of PPC by means of the mathematical modeling. At the tactical level it is determined lot sizing and their respective delivery date. At the operational level it is defined the products/product family scheduling. According to Loveland et al. (2007)Loveland, J. L., Monkman, S. K., & Morrice, D. J. (2007). Dell uses a new production scheduling algorithm to Accommodate Increased Product Variety. Interaces, 37(3), 209-219. http://dx.doi.org/10.1287/inte.1060.0264.
http://dx.doi.org/10.1287/inte.1060.0264...
, a formulation that communicates the tactical and operational decisions pursues to establish better communication and organization of the shop floor.

Currently, the company’s PPC seeks to produce every week only the expected demand for this time interval, trying not to accumulate stocks of previous periods, but it incurs in the use of overtime when needed. The company believes that the demand uncertainties are relatively large. However, PPC defines only the need of production hours and it does not consider the time spent in scheduling. This scheduling is not planned in the initial program, leaving it to the operational level. Thus, many production plans set by the PPC become infeasible on the shop floor or they require large amounts of overtime work. This is the crucial problem to the company today. The proposed formulation should provide the anticipation of production in periods when there is idle capacity, and it seeks better production sequences, i.e., with fewer setups.

The company sales forecast is made by internal and external forecasts. The first week of planning has real demands and by increasing the distance of the planning period, the demand is made by forecasts. All demands are available in the integrated management system of the company. An employee performs the system to check the requests, returning information about the inventory. At the end of this process, it is possible to determine how much manufacture of each product/product family.

The production scheduling is defined in the PPC team meeting which, based on tacit knowledge, defines the production sequence for the next few weeks in order to reduce the idle time and ignoring the stock costs. This process spends around 8 hours per week, but it does not guarantee the optimality of the productions scheduling, i.e., it is not known how close the proposed solution is from the optimal solution, since the proposed sequence only sets the production scheduling, without considering the setup times. Then it is necessary to make additional calculations to check the feasibility of the demand meeting and delivery dates obedience.

It is interesting to highlight that there is no interaction between the tactical and operational decision levels in determining the amount of goods to be produced. Therefore, there is no guarantee that the production set by the PPC can be sequenced and manufactured. The sales orders are supplied by the finished product inventories or, if there are not the good in stock, they are converted into production orders. The sequencing of these production orders should be done respecting the established demand.

The company has a 5% rate of overdue delivery because of the lack of capacity on the production line. Currently, 20% of the available line time is used in the machine setup, thus, minimizing this time results in increasing the capacity and reducing the delays in delivery. Therefore, there is a need to create a mathematical model that organizes the production line, reducing the preparation time and increasing the time for production. This formulation should look for the best production sequence in order to minimize the costs inherent to the process.

The PPC has chosen to work with a planning period of only seven days, even providing four weeks to the sales department. This period was chosen based on the information reliability, and in the current week the requests are made based on actual demands. The PPC department, to increase productivity, allows anticipating the production and attending the orders before the expected date, however, this can lead to unnecessary stock.

4 Proposed formulations and solution method

This study presents three mathematical models for integrated lot sizing and scheduling with the objective of minimizing the unmet demand and inventory costs, considering sequence-dependent setup times. These models are: one with continuous variables, one reference approach with time-indexed variables and a new formulation proposed by the authors.

The first approach, denominated Mixed-Binary-Integer Linear Programming with Continuous Time Horizon (MBILP-CH), is based on Manne (1960)Manne, A. S. (1960). On the job-shop scheduling problem. Operations Research, 8(2), 219-223. http://dx.doi.org/10.1287/opre.8.2.219.
http://dx.doi.org/10.1287/opre.8.2.219...
, Carvalho & Santos (2006)Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO. and Santos (2006)Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte.. This formulation presents continuous, integer and binary variables and a continuous time planning horizon. The second approach is based on works of Toledo et al. (2007)Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009.
http://dx.doi.org/10.1590/S0101-74382007...
, Toso et al. (2009)Toso, E. A., Morabito, R., & Clark, A. R. (2009). Lot sizing and sequencing optimization at an animal-feed plant. Computers & Industrial Engineering, 57(3), 813-821. http://dx.doi.org/10.1016/j.cie.2009.02.011.
http://dx.doi.org/10.1016/j.cie.2009.02....
and Ferreira et al. (2010)Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007.
http://dx.doi.org/10.1016/j.cor.2009.06....
. This is denominated Mixed-Binary-Integer Linear Programming with Discretized Time Horizon (MBILP-DH) and it presents time-indexed variables, with the planning horizon discretized into s¯ sub-periods. In this formulation, the s¯ parameter is at most equal to the number of product families j¯, thus all families can be produced (but do not need to be). Finally, the formulation proposed, denominated Mixed-Binary-Integer Linear Programming with Discretized Time Horizon (MBILP-DHP), inspired by previous formulations presented and by the works of Sousa & Wolsey (1992)Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059.
http://dx.doi.org/10.1007/BF01586059...
and Henriques et al. (2010)Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO..

The MBILP-DH and MBILP-DHP formulations present time-indexed variables (discretized planning horizon), and as analyzed by Keha et al. (2009)Keha, A. B., Khowala, K., & Fowler, J. W. (2009). Mixed integer programming formulations for single machine scheduling problems. Computers & Industrial Engineering, 56(1), 357-367. http://dx.doi.org/10.1016/j.cie.2008.06.008.
http://dx.doi.org/10.1016/j.cie.2008.06....
this implies in tighter bounds. In the MBILP-DHP formulation the time is discretized in s¯ sub-periods with size equal to the production capacity in hours available. This increased planning horizon leads to a larger number of variables and constraints than MBILP-DH, and consequently, it restricts the size of instances that can be solved.

Keha et al. (2009)Keha, A. B., Khowala, K., & Fowler, J. W. (2009). Mixed integer programming formulations for single machine scheduling problems. Computers & Industrial Engineering, 56(1), 357-367. http://dx.doi.org/10.1016/j.cie.2008.06.008.
http://dx.doi.org/10.1016/j.cie.2008.06....
and Unlu & Mason (2010)Unlu, Y., & Mason, S. J. (2010). Evaluation of mixed integer programming formulations for non-preemptive parallel machine scheduling problems. Computers & Industrial Engineering, 58(4), 785-800. http://dx.doi.org/10.1016/j.cie.2010.02.012.
http://dx.doi.org/10.1016/j.cie.2010.02....
showed that the lower bounds obtained from the formulations based on the proposal of the Sousa & Wolsey (1992)Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059.
http://dx.doi.org/10.1007/BF01586059...
were strong, but the LP relaxations are harder to solve compared to the other formulations. However, the computational experiments from De Paula et al. (2010)De Paula, M. R., Mateus, G. R., & Ravetti, M. G. (2010). A non-delayed relax-and-cut algorithm for scheduling problems with parallel machines, due dates and sequence-dependent setup times. Computers & Operations Research, 37(5), 938-949. http://dx.doi.org/10.1016/j.cor.2009.07.006.
http://dx.doi.org/10.1016/j.cor.2009.07....
suggest that when sequence-dependent setup times are introduced, the LP relaxation bounds in the time-indexed formulation are not as strong. Nogueira (2014)Nogueira, T. H. (2014). Single machine scheduling problems with sequence dependent setup times (Tese de doutorado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte. highlights this fact and proposes a family of valid inequalities to improve the lower bounds obtained with sequence-dependent setup times. Furthermore, the author expounds on when the number of products or the size of the planning time horizon increases the mathematical formulations are unable to solve problems in the commercial solver.

4.1 Problem modeling

The MBILP-CH and MBILP-DH formulation are based on Manne (1960)Manne, A. S. (1960). On the job-shop scheduling problem. Operations Research, 8(2), 219-223. http://dx.doi.org/10.1287/opre.8.2.219.
http://dx.doi.org/10.1287/opre.8.2.219...
, Carvalho & Santos (2006)Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO., Santos (2006)Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte., Toledo et al. (2007)Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009.
http://dx.doi.org/10.1590/S0101-74382007...
, Toso et al. (2009)Toso, E. A., Morabito, R., & Clark, A. R. (2009). Lot sizing and sequencing optimization at an animal-feed plant. Computers & Industrial Engineering, 57(3), 813-821. http://dx.doi.org/10.1016/j.cie.2009.02.011.
http://dx.doi.org/10.1016/j.cie.2009.02....
and Ferreira et al. (2010)Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007.
http://dx.doi.org/10.1016/j.cor.2009.06....
. The MBILP-DHP formulation is a new proposal, inspired by the works of Sousa & Wolsey (1992)Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059.
http://dx.doi.org/10.1007/BF01586059...
and Henriques et al. (2010)Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO.. All formulations consider the following considerations: i) the studied problem is treated as a single machine problem, considering rolling horizon strategy; ii) the lots have different sizes and its sequence impact on the total time spent on setups. When there is no risk of contamination between families the setup time is short, otherwise it is longer and compromises the total time available for production. The sets for the formulations are:

  • - J refers to the set of product families to be produced, with J={1,,j¯}.

  • - T refers to the set of periods in the planning horizon, with T={1,,t¯}.

  • - S refers to the set of sub-periods in the planning horizon, with S={1,,s¯}.

The indexes used in the mathematical models are:

  • - i refers to the product family considered, such that iJ.

  • - t indicates the period of the planning horizon considered, such that tT.

  • - s indicates the sub-period of the planning horizon considered, such that sS.

The parameters considered for the formulations are:

  • - dit: Demand of the product family i in period t.

  • - Smi: Minimal setup time to produce the product family i.

  • - pi: Processing time of the product family i.

  • - Ct: Total capacity in hours in period t.

  • - Stij: Setup time to changeover from the product family i to the product family j.

  • - Hi: Inventory cost of the product family i.

  • - Bi: Backorder cost of the product family i.

  • - M: Large value, which is given by the total time taken to produce all the demand of the first week of planning plus the maximum time spent for preparing the production of the product family i to the product family j, as can be seen in Nogueira (2014)Nogueira, T. H. (2014). Single machine scheduling problems with sequence dependent setup times (Tese de doutorado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte., which is given by:

    M=iJ(pidi1)+iJmaxjJStij(1)

The decision variables used in the formulations are:

  • - Iit: Continuous variable that indicates the amount in stock of the product family i in period t.

  • - qit: Continuous variable that indicates the amount produced of the product family i in period t.

  • - Iit: Continuous variable that indicates the backorder of the product family i in period t.

  • - ri: Continuous variable that indicates the starting time of the production of the product family i.

  • - βijs: Binary variable that indicates the production (βijs= 1) or not (βijs= 0) of the product family j after the production of the product family i in sub-period s.

  • - vit: Binary variable that indicates the production (vih= 1) or not (vih= 0) of the product family i in period t.

  • - xis: Binary variable that indicates the production (xis= 1) or not (xis= 0) of the product family i in sub-period s.

  • - yij: Binary variable that indicates the production (yij= 1) or not (yij= 0) of the product family j after the production of the product family i.

4.1.1 MBILP-CH – mixed-binary-integer linear programming with continuous time horizon

The formulation is evidenced below:

M i n i m i z e i J , t T ( H i I i t + B i I i t ) (2)

Subject to:

I i t = I i , t 1 + q i t d i t + I i t i J , t T , (3)
i J ( v i t S m i + q i t p i ) C t t = 2 t ¯ , (4)
q i t p i C t v i t i J , t = 2 t ¯ , (5)
r j r i + S t i j v i 1 + p i q i 1 M ( 1 y i j ) i J , j J , i j , (6)
y i j + y j i = 1 i J , j J , i j , (7)
r i + p i q i 1 C 1 v i 1 i J , (8)
y i j { 0,1 } i J , j J , i j , (9)
v i t { 0,1 } i J , t T , (10)
q i t , I i t , I i t 0 i J , t T , (11)
r i 0 i J . (12)

The problem aims to minimize the inventory costs and the backorder costs, as shown in the Constraint 2. In the Expression 3 we have the line balancing constraint in which the amount of stock Iit of the product family i in the end of period t is equal to the stock of the previous period Ii,t1 increased of the production of period t,qit, and backorder of the same period Iit, reducing the demanded quantity dit. The Constraint 4 limits the capacity of the factory, showing that the minimum amount of hours of setup iJ(vitSmi) plus the total production time iJ(qitpi) of the product family i must be smaller than the total time capacity of the factory Ct, from the period 2. If the product family i is produced in the period t, the total time qitpi for its production must be less than the total capacity of the factory Ctvit, as shown in the Constraint 5, being valid from the second planning period. The Constraint 6 requires that the production start date rj of the product family j is equivalent to the starting date ri of the production of the product family i plus the time spent in preparation for the exchange of the product family i to the j,Stijvi1added to the total amount of production time of the product family i in the first time period, piqi1. Note that rj must obey to this expression when the manufacture of the product family j occurs after the manufacture of the product family i (yij=1). Otherwise, (yij=0), the Expression 6 will have the subtraction of a very large value, denoted by M, so that it will not restrict the amount rj. The Constraint 7 states that, within a certain range of time, there will be exchange from the product family i to j or the contrary, i.e., it will be only one exchange during this period. In the Constraint 8 it is possible to see that the production beginning time of i plus the lead time of this product family should be less than the period 1 capacity, if the product family i is produced in this period. The Constraints 9, 10, 11 and 12 define the domains of the variables.

4.1.2 MBILP-DH – mixed-binary-integer linear programming with discretized time horizon

Following the modeling for this formulation.

M i n i m i z e i J , t T ( H i I i t + B i I i t ) (13)

Subject to:

I i t = I i , t 1 + q i t d i t + I i t i J , t T , (14)
i J ( v i t S m i + q i t p i ) C t t = 2 t ¯ , (15)
i J , j J , s S , i j ( β i j s S t i j ) + i J ( q i 1 p i ) C 1 , (16)
q i t p i C t v i t i J , t = 2 t ¯ , (17)
q i 1 p i C 1 s S x i s i J , (18)
i J x i s = 1 s S , (19)
β i j s x i , s 1 + x j s 1 i J , j J , s = 2 s ¯ , i j , (20)
β i j s { 0,1 } i J , j J , s S , i j , (21)
v i t { 0,1 } i J , t T , (22)
x i s { 0,1 } i J , s S , (23)
q i t , I i t , I i t 0 i J , t T . (24)

The objective function shown in the Constraint 13 is the same as already discussed in the Constraint 2, as well as the Constraints 14 and 15, which have the same meaning of Constraints 3 and 4, respectively. Given the production in sub-periods, the preparation of the production line is required when the production of a product family j in the sub-period s begins after the end of the production of the family i, considering a total capacity into productive time in the first planning period, C1, the sum of the setup times and production times, as shown in the Expression 16. The Constraint 17 shows that the time for the production of each product family i in a given period of time should be less than the total capacity in time Ct in period t. In the Constraint 18 we have that if the product family i is produced in period 1 its production time should be less than the capacity in this time period. The Constraint 19 shows that only a product family shall be produced by sub-period s. The Constraint 20 shows that there will be only production of the product family j after the production of the product family i in the sub-period s if there are production of i in sub-period s-1 and production of j in sub-period s, i.e., there will be a change in the product family i to the product family j. The Expressions 21, 22, 23 and 24 define the domains of the variables.

4.1.3 MBILP-DHP – mixed-binary-integer linear programming with discretized time horizon

The proposed formulation, as already mentioned, is based on Sousa & Wolsey (1992)Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059.
http://dx.doi.org/10.1007/BF01586059...
and Henriques et al. (2010)Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO.. This is a new formulation, inspired by scheduling problems, however, requiring particular settings and definitions. For this formulation a new parameter is necessary:

  • - ai: Product family i production rate in each sub-period.

Are also used the new variables:

  • - zis: Binary variable indicating the beginning (zis= 1) or not (zis= 0) of the product family i production in sub-period s.

  • - wis: Binary variable indicating the end (wis= 1) or not (wis= 0) of the product family i production in sub-period s.

The proposed formulation is presented below.

M i n i m i z e i J , t T ( H i I i t + B i I i t ) (25)

Subject to:

I i , t 1 + q i t + I i t = d i t + I i t i J , t T , (26)
i J ( v i t S m i + q i t p i ) C t t = 2 t ¯ , (27)
q i t p i C t v i t i J , t = 2 t ¯ , (28)
q i 1 = a i ( s S s w i s s S s z i s + s S z i s ) i J , (29)
s S w i s = s S z i s i J , (30)
s S z i s 1 i J , (31)
w i s + s s = s min ( s + S t i j + p i 1, s ¯ ) z j , s s 1 s S , i J , j J , i j , (32)
s = s 1 s 2 w i s z i , s 1 + z j , s 2 1 i J , j J , s 1 S , s 2 S , s 2 s 1, i j , (33)
s = s 1 s 2 z i s w j , s 1 + w i , s 2 1 i J , j J , s 1 S , s 2 S , s 2 s 1, i j , (34)
w i s , z i s { 0,1 } i J , s S , (35)
v i t { 0,1 } i J , t T , (36)
q i t , I i t , I i t 0 i J , t T . (37)

The Constraints 25, 26, 27 and 28 have the same meaning as the Constraints 2, 3, 4 and 5, respectively. The amount to be made of the product family i in the first period is given by the Constraint 29, in which this quantity is calculated based on the time spent and in the production rate, ai. The Constraint 30 ensures that the entire product family i which has its production started must be completed, guaranteeing the processing end of all items started. The Constraint 31 determines that each product family has its production started only once in all sub-periods s. The Constraint 32 ensures that if the product family i is allocated to a sub-period s, so no other product family j can be allocated until the end of this sub-period, while respecting the total capacity of the first week of planning. In the Constraint 33 it is set that between two beginnings of production will always be an end and the Constraint 34 determines that between two endings of production will always be a start. The Constraints 35, 36 and 37 present the domains of the variables.

The proposed formulation, MBILP-DHP, presents homogeneity in its time of the sub-periods, since the length thereof does not depend on the lead time of each product family. Thus, directly by the values of variables zis and wis it is possible to determine the chronological position of certain product family, as well as the precedence relations of the whole production.

Both the MBILP-CH and the MBILP-DH only show the start date of the production of each product family, there being no temporal detail during manufacturing. This fact imposes that the production of all demand for certain product family occurs once in the period. In addition, attention should be given to the fact that the MBILP-CH presents the parameter M, a large number, which is often determined arbitrarily, worsening the limits obtained.

Like the first two formulations presented, the latter limits by the Restriction 31 that, in all sub-periods, a product family initiate its production only once. This assumption was adopted so that the MBILP-DHP possesses the same characteristics of other formulations discussed here. However, if it has been suppressed, the formulation is able to realize interruption in the production of a product family to begin another and, where possible, complete the production of this first, characterizing the preemptive scheduling.

Analyzing the problems of PPC, this characteristic can benefit managers to adapt the production more easily to unexpected and urgent demands of some products. Thus, the production of these can be prioritized without compromising the remaining scheduling. The imposition that the entire necessary amount of a product/product family should be manufactured at a single time per period may generate some practical complications.

5 Computational results

Extensive computational experiments are performed to identify the strength and the weaknesses of each proposed formulation as a support decision tool. In order to analyze the performance of the mathematical formulations same parameters will be varied. A specific benchmark including these different features and characteristics was created for this purpose.

5.1 Benchmarking

Three different classes of instances are created based on real data. All instances classes have four weeks for the planning horizon. In the MBILP-DHP formulation, each week is divided into 112 sub-periods of 1 hour (2 shifts of 8 hour for each day of the week). In MBILP-DH formulation each week is divided in an amount equal to the number of product families to be produced. Therefore, in this formulation, the size of each sub-period is flexible, i.e., it will always depend on the number of product families that will be produced in each week. For all formulations were considered the following distinct product family quantities: 2, 3, 4, 5, 6, 7, 10, 15 and 20. Furthermore, the inventory of any product family at the start of the planning horizon is zero.

All parameters of the instances are randomly generated from a uniform distribution and their minimal and maximal values are based on specific scale parameters listed in Table 2.

Table 2
Distribution values of the instances.

The j¯ parameter refers to the total number of product families in J. The values of the demand for each family, the processing time, the setup times, the cost of inventory and the cost of backorder are based on real data. The demand for each family is generated by three different ways (Classes 1, 2 and 3) to capture several aspects of real situations and their influences. The amount is generated by a parameter α1 with values 0.75, 1.50 and 3.00 for each class respectively. For each class, three independent instances are considered with size j¯{2,3,4,5,6,7,10,15,20}. Thus, 81 instances are randomly and independently generated. All instances are slightly modified to satisfy the triangle inequality (StijStil+StljiJ,jJ,lJ,ijl). The M value was defined by Equation 1.

5.2 Results

The mathematical formulations were modeled and solved using AMPL and CPLEX 12.1 with default settings. The experiments were run on a Windows 7 with a single 2.2 GHz processor and 4GB memory. The runs were concluded after one hour of CPU time.

5.2.1 Specific results

5.2.1.1 Validation of the formulations solutions

In order to evaluate and to compare the solution of the three formulations, this section aims to analyze the solutions of each one, taking as input the same data. First it was chosen one instance problem with three product families to be processed, with four sub-periods. All formulations managed to solve at optimality and the resolution times for MBILP-CH, MBILP-DH and MBILP-DHP were, respectively, 0.05, 0.55 and 68.25 seconds.

The lot sizing variables obtain identical results for the three formulations, satisfying the demand without any inventory or backorder. However, these formulations present different solutions for the scheduling of the first period for the same instance problem, emphasizing the difference between them.

For the MBILP-CH the product families schedule is 2-3-1, with their start times (ri) 0, 30 and 38. In this formulation it is possible to identify directly by decision variables the schedule and the start times. Although there is no complexity in these calculations, it is clear that this formulation requires auxiliary procedures to identify the production completion times.

The MBILP-DH presents the optimal schedule 3-1-2. The solution shows the number of sub-periods equals to the amount of product families, therefore there is no temporal notion about the production beginning and end of each product family. Again, this formulation also requires auxiliary procedures to provide more details of the solution.

For the MBILP-DHP the product families schedule is 2-1-3, with their start times (zis) and completion times (wis): 3 and 30, 45 and 96, 106 and 111, respectively. The decision variables allow a temporal notion of the schedule, and it is evident by them that the solution presents slack, therefore, if necessary, more product families can be added for the first period.

The formulation MBILP-DHP has longer resolution time than the other formulations, however the elimination of the Restriction 31, as already mentioned, enables the preemptive scheduling. This provides flexibility to start and complete the production of a product family more than once in the same period. This choice can be useful to anticipate the production of subsequent periods, if the cost of backorder is higher than the cost of the generated inventory.

5.2.1.2 Comparation with company's results

As mentioned, the company decides the schedule of the families to be produced just for the first week of the planning horizon, not anticipating the production of next weeks, preferring to incur in overtime when necessary. This practical may cause idleness in production line and backorders.

This study aims to define mathematical formulations that allow the studied company anticipates the production of other weeks for the previous weeks with idleness, reducing the costs of the backorder and delivery delays. Furthermore, the forecasts for more distant periods are likely to change once the horizon is rolled forward and managers often have to revise the plans to cope with disruptive events. For this, the production planning should be done considering a rolling horizon, scheduling the product families for the first week and just defining the lot sizing for the remaining weeks.

In general, the mathematical formulations present an average delay of 0% for the product families to instances of the classes 1 and 2 and 7% for the Class 3, the last has tighter demand in relation to other classes. The total average delay presented by formulations is approximately 2%, while the company historical average delay is 4%. It is noteworthy that the data is based on real historical values of the company, but there is no guarantee that the behavior exhibited by the mathematical formulations is exactly the identical as the real company results, even if the instance problems used in this study were based on real historical data.

5.2.2 General results – performance evaluation of the formulations

To analyze the differences between the formulations, it was compared the optimality GAP (GAPInteger) within 3,600 seconds, the LP relaxation GAP, CPU times and its dimensions. The LP relaxation gap (GAPRelax) is defined as the relative difference between the best integer solution found for each instance and the LP relaxation value, divided by the best integer solution. The results of the experiments and analysis are presented in Tables 3 and 4. The Table 3 depicts the average GAP results and the average computational times for the presented formulations considering each instance class problem, while Table 4 shows the dimension of the formulations.

Table 3
Results related to each class and each product family for formulations MBILP-CH, MBILP-DH and MBILP-DHP.
Table 4
Order of complexity for each formulation.

In Table 3, the first two columns refer to the instance class and the number of product families. For each instance class its average and its standard deviation are calculated. The TRelax and TInteger indicate the average CPU times for the LP relaxation and the mixed-integer programming (MIP) problem, respectively. The “% Inst. Resol.” is the percentual of the instances solved within 3,600 seconds for LP relaxation and MIP problem.

As an example, the “Class 1” and the “Product Family 20” in Table 3 indicate that 20 distinct product families are considered, with its characteristics defined in the “Class 1” in “Section 5.1”. Therefore, as already presented, three results were generated for the “Class 1” and the “Product Family 20” and its averages for the GAPs and the computational times are calculated. Furthermore, its average and standard deviation values are calculated for each instance class to compare the performance of the formulations.

For instance classes 1 and 2 with up to 5 product families all analyzed formulations have GAP near to 0%, whereas them managed to optimality solve in most cases, for both LP relaxation and MIP problem. It is also observed a reduced computational time, which justifies the use of the formulations for a small number of product families. In the Class 3, the LP relaxation of the mathematical formulations presents higher GAP values than classes 1 and 2. The higher GAPRelax is presented by MBILP-CH with value of 75.6%, however this formulation has computational time near to 0 seconds for all instances. The results of the Class 3 were expected due to have a tighter demand than other classes.

For the instance classes greater than 5 product families, the MIP formulation MBILP-DH has GAP near to 0% for all problems. On the other hand, for large problem instances the MBILP-CH presents worse lower bounds than MBILP-DH. The MBILP-CH has GAP values near to 100% with similar computational time to MBILP-DH. The LP relaxation also presents similar GAPs to MIP problems, having few instances with solutions near to the optimal.

The formulations MBILP-CH, MBILP-DH and MBILP-DHP solve 100%, 100% and 67% of the instance problems for the LP relaxations, respectively, and 72%, 77% and 41% for the MIP formulations. As the size of the input data increases, the GAP and the computational time increase faster for MBILP-DHP, solving smaller number of LP and MIP instances than other formulations. This is due to number of constraints and variables associated with MBILP-DHP which increase the model’s size faster than other formulations. It must be highlighted that in several occasions the formulation was unable to load the whole problem into the solver. In those cases the GAP and its computational time were defined by “-”.

The Table 4 presents the order of complexity for each formulation. For the formulations, “Binary Variables” indicate the number of associated variables and “Constraints” the number of associated constraints.

The formulation MBILP-DH presents in its worst case, s¯=j¯, therefore, its representation is only in function of j¯ in Table 4. The complexity of the formulations MBILP-CH and MBILP-DH in this article have a polynomial number of constraints and variables in the input data. However, this is not the case for MBILP-DHP, as they also are strongly dependent on j¯ and s¯. It is worth noting that as s¯j¯, s¯j¯ (see Keha et al. (2009)Keha, A. B., Khowala, K., & Fowler, J. W. (2009). Mixed integer programming formulations for single machine scheduling problems. Computers & Industrial Engineering, 56(1), 357-367. http://dx.doi.org/10.1016/j.cie.2008.06.008.
http://dx.doi.org/10.1016/j.cie.2008.06....
for more details), MBILP-DHP formulation will increase its size faster than other formulations. In this paper the size of the s¯ was defined in “Section 5.1”.

As it can be seen in Table 4, the MBILP-CH has a smaller number of constraints and variables than other presented formulations. The MBILP-DH has identical number of variables with slightly larger number of constraints than MBILP-CH. Finally, MBILP-DHP formulation has a considerably larger number of variables and constraints, due tos¯j¯, i.e., the number of sub-periods is much greater than the number of product families, requiring a lot of memory space.

6 Conclusion

The MBILP-DHP, using random data based on actual data, showed satisfactory results, adequately representing the decision making process. In addition, it is emphasized the possibility of preemptive scheduling, allowing more flexibility in the manufacture of the product families. This flexibility permits that in the same time horizon a product family manufacture can be initiated and completed more than once, depending on the backorder and inventory costs. Thus, this formulation has a key differential aspect in the generation of the production scheduling when compared to the formulations that do not allow preemptive scheduling.

With the obtained results, it was possible to notice that the MBILP-CH formulation presented ease of resolution, because this formulation has a fewer number of constraints and variables, but showed weaker bounds when compared to the other formulations. The MBILP-DH formulation has a greater number of constraints and variables, requiring a longer computational time, but its use is justified by the fact of possessing stronger bounds, resulting in a closest solution to the optimum. The solution methods such as relax-and-fix method could be used, given that it provides a good solution for this type of formulations in a reasonable computational time. A deep discussion about this method can be seen in Kelly & Mann (2004)Kelly, J. D., & Mann, J. L. (2004). Flowsheet decomposition heuristic for scheduling: a relax-and-fix method. Computers & Chemical Engineering, 28(11), 2193-2200. http://dx.doi.org/10.1016/j.compchemeng.2004.03.009.
http://dx.doi.org/10.1016/j.compchemeng....
.

The MBILP-DHP formulation is an alternative to literature formulations, returning similar results to the MBILP-DH. However, the former requires a greater computational time, due to the growing order behavior of its variables and constraints, being better used for Lagrangian Relaxation. As advantages, it presents sub-periods with identical lengths, which ensures the homogeneity of production time.

Acknowledgements

The first author thanks the financial support of the State of Minas Gerais Research Support Foundation – FAPEMIG.

  • Financial support: FAPEMIG – first author.

Referências

  • Allahverdi, A., Ng, C. T., Cheng, T. C. E., & Kovalyov, M. Y. (2008). A survey of scheduling problems with setup times or costs. European Journal of Operational Research, 187(3), 985-1032. http://dx.doi.org/10.1016/j.ejor.2006.06.060
    » http://dx.doi.org/10.1016/j.ejor.2006.06.060
  • Araujo, S. A., Arenales, M. N., & Clark, A. R. (2004). Dimensionamento de lotes e programação do forno numa fundição de pequeno porte. Gestão & Produção, 11(2), 165-176. http://dx.doi.org/10.1590/S0104-530X2004000200003
    » http://dx.doi.org/10.1590/S0104-530X2004000200003
  • Araujo, S. A., Arenales, M. N., & Clark, A. R. (2007). Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups. Journal of Heuristics, 13(4), 337-358. http://dx.doi.org/10.1007/s10732-007-9011-9
    » http://dx.doi.org/10.1007/s10732-007-9011-9
  • Arenales, M., Armentano, V. A., Morabito, R., & Yanasse, H. H. (2007). Pesquisa operacional. 6 ed. Rio de Janeiro: Elsevier. 524 p.
  • Bernardes, E. D., Araujo, S. A., & Rangel, S. (2010). Reformulação para um problema integrado de dimensionamento e sequenciamento de lotes. Pesquisa Operacional, 30(3), 637-655.
  • Brahimi, N., Dauzere-Peres, S., Najid, N. M., & Nordli, A. (2006). Single item lot sizing problems. European Journal of Operational Research, 168(1), 1-16. http://dx.doi.org/10.1016/j.ejor.2004.01.054
    » http://dx.doi.org/10.1016/j.ejor.2004.01.054
  • Brasil. Ministério de Minas e Energia – MME. (2009). Recuperado em 15 de maio de 2014, de http://www.mme.gov.br/mme
    » http://www.mme.gov.br/mme
  • Bustamante, L. (2007). Minimização do custo de antecipação e atraso para o problema de sequenciamento de uma máquina com tempo de preparação dependente da sequência: aplicação em uma usina siderúrgica (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte.
  • Buxey, G. (1989). Production scheduling: practice and theory. European Journal of Operational Research, 39(1), 17-31. http://dx.doi.org/10.1016/0377-2217(89)90349-4
    » http://dx.doi.org/10.1016/0377-2217(89)90349-4
  • Carvalho, C. R. V., & Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de sequenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química. In Anais do 38º Simpósio Brasileiro de Pesquisa Operacional (pp. 1922-1933). Goiânia: SBPO.
  • Chen, J., & Askin, R. G. (2009). Project selection, scheduling and resource allocation with time dependent returns. European Journal of Operational Research, 193(1), 23-34. http://dx.doi.org/10.1016/j.ejor.2007.10.040
    » http://dx.doi.org/10.1016/j.ejor.2007.10.040
  • Clark, G. E. A., Almada-Lobo, B., & Almeder, C. (2011). Lot sizing and scheduling: industrial extensions and research opportunities. International Journal of Production Research, 49(9), 2457-2461. http://dx.doi.org/10.1080/00207543.2010.532908
    » http://dx.doi.org/10.1080/00207543.2010.532908
  • De Paula, M. R., Mateus, G. R., & Ravetti, M. G. (2010). A non-delayed relax-and-cut algorithm for scheduling problems with parallel machines, due dates and sequence-dependent setup times. Computers & Operations Research, 37(5), 938-949. http://dx.doi.org/10.1016/j.cor.2009.07.006
    » http://dx.doi.org/10.1016/j.cor.2009.07.006
  • Defalque, C. M., Rangel, S., & Ferreira, D. (2011). Usando o ATSP na modelagem do problema integrado de produção de bebidas. TEMA. Tendências em Matemática Aplicada e Computacional, 12(3), 195-209. http://dx.doi.org/10.5540/tema.2011.012.03.0195
    » http://dx.doi.org/10.5540/tema.2011.012.03.0195
  • Du, J., & Leung, J. Y. T. (1990). Minimizing total tardiness on one machine is NP-hard. Mathematics of Operations Research, 15(3), 483-495. http://dx.doi.org/10.1287/moor.15.3.483
    » http://dx.doi.org/10.1287/moor.15.3.483
  • Fernandes, F. C. F., & Santoro, M. C. (2005). Avaliação do grau de prioridade e do foco do planejamento e controle da produção (PCP): modelos e estudos de casos. Gestão & Produção, 12(1), 25-38. http://dx.doi.org/10.1590/S0104-530X2005000100004
    » http://dx.doi.org/10.1590/S0104-530X2005000100004
  • Ferreira, D., Morabito, R., & Rangel, S. (2009). Solution approaches for the soft drink integrated production lot sizing and scheduling problem. European Journal of Operational Research, 196(2), 697-706. http://dx.doi.org/10.1016/j.ejor.2008.03.035
    » http://dx.doi.org/10.1016/j.ejor.2008.03.035
  • Ferreira, D., Morabito, R., & Rangel, S. (2010). Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Computers & Operations Research, 37(4), 684-691. http://dx.doi.org/10.1016/j.cor.2009.06.007
    » http://dx.doi.org/10.1016/j.cor.2009.06.007
  • Henriques, R. S., Carvalho, C. R. V., & Cunha, A. S. (2010). Um modelo com variáveis indexadas no tempo para a integração do Dimensionamento de Lotes e Sequenciamento em uma máquina com tempos de preparação. In Anais do XLII Simpósio Brasileiro de Pesquisa Operacional. Bento Gonçalves: SBPO.
  • Keha, A. B., Khowala, K., & Fowler, J. W. (2009). Mixed integer programming formulations for single machine scheduling problems. Computers & Industrial Engineering, 56(1), 357-367. http://dx.doi.org/10.1016/j.cie.2008.06.008
    » http://dx.doi.org/10.1016/j.cie.2008.06.008
  • Kelly, J. D., & Mann, J. L. (2004). Flowsheet decomposition heuristic for scheduling: a relax-and-fix method. Computers & Chemical Engineering, 28(11), 2193-2200. http://dx.doi.org/10.1016/j.compchemeng.2004.03.009
    » http://dx.doi.org/10.1016/j.compchemeng.2004.03.009
  • Lawler, E. L. (1976). Combinatorial optimization: networks and matroids. New York: Holt, R. & Winston. 362 p.
  • Leung, J. Y.-T. (2004). Handbook of scheduling: algorithms, models, and performance analysis. Boca Raton: Chapman & Hall /CRC. 1224 p.
  • Loveland, J. L., Monkman, S. K., & Morrice, D. J. (2007). Dell uses a new production scheduling algorithm to Accommodate Increased Product Variety. Interaces, 37(3), 209-219. http://dx.doi.org/10.1287/inte.1060.0264
    » http://dx.doi.org/10.1287/inte.1060.0264
  • Magnesita Refratários. (2015). Soluções refratárias. Recuperado em 23 de fevereiro de 2015, de http://ri.magnesita.com
    » http://ri.magnesita.com
  • Manne, A. S. (1960). On the job-shop scheduling problem. Operations Research, 8(2), 219-223. http://dx.doi.org/10.1287/opre.8.2.219
    » http://dx.doi.org/10.1287/opre.8.2.219
  • Molina, F., Morabito, R., & Araujo, S. A. (2013). Modelos matemáticos para problemas de dimensionamento de lotes com restrições de capacidade e custos de transporte. Gestão & Produção, 20(3), 573-586. http://dx.doi.org/10.1590/S0104-530X2013000300006
    » http://dx.doi.org/10.1590/S0104-530X2013000300006
  • Nemhauser, G. L., & Wolsey, L. A. (1988). Integer and combinatorial optimization. New York: Wiley.
  • Nogueira, T. H. (2008). Modelagem do sequenciamento da ensilagem em processos industriais de formação de receitas (Dissertação de mestrado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte.
  • Nogueira, T. H. (2014). Single machine scheduling problems with sequence dependent setup times (Tese de doutorado). Departamento de Engenharia de Produção, Universidade Federal de Minas Gerais, Belo Horizonte.
  • Pinedo, M. L. (2012). Scheduling: theory, algorithms, and systems. 4 ed. Nova York: Springer.
  • Pochet, Y., & Wolsey, L. A. (2006). Production planning by mixed integer programming (Springer Series in Operations Research and Financial Engineering). Nova York: Springer. 499 p.
  • Ramos, R. S., & Oliveira, F. B. (2011). Uma abordagem ao problema de sequenciamento em uma máquina com penalidades por antecipação e atraso da produção por meio de algoritmos evolutivos. Conexão Ciência, 6(2), 21-37.
  • Rego, M. F. (2013). Algoritmos multiobjetivos para o problema de sequenciamento de tarefas em uma máquina com tempo de preparação dependente da sequência e da família (Dissertação de mestrado). Universidade Federal de Ouro Preto, Ouro Preto.
  • Santos, A. M. (2006). Dimensionamento de lote de produção em um problema de seqüenciamento de uma máquina com tempo de preparação: aplicação a uma indústria química (Dissertação de mestrado). Universidade Federal de Minas Gerais, Belo Horizonte.
  • Santos, M. O., & Massago, S. (2007). Um método heurístico para o problema de dimensionamento e sequenciamento de lotes com custos e tempo das preparações sequencia- dependentes. Anais do 39º Simpósio Brasileiro de Pesquisa Operacional. Fortaleza: SBPO.
  • Seeanner, F., & Meyr, H. (2013). Multi-stage simultaneous lot-sizing and scheduling for flow line production. OR-Spektrum, 35(1), 33-73. http://dx.doi.org/10.1007/s00291-012-0296-1
    » http://dx.doi.org/10.1007/s00291-012-0296-1
  • Shim, I.-S., Kim, H.-C., Doh, H.-H., & Lee, D.-H. (2011). A two-stage heuristic for single machine capacitated lot-sizing and scheduling with sequence-dependent setup costs. Computers & Industrial Engineering, 61(4), 920-929. http://dx.doi.org/10.1016/j.cie.2011.06.002
    » http://dx.doi.org/10.1016/j.cie.2011.06.002
  • Sousa, J. P., & Wolsey, L. A. (1992). A time indexed formulation of non-preemptive single machine scheduling problems. Mathematical Programming, 54(1-3), 353-367. http://dx.doi.org/10.1007/BF01586059
    » http://dx.doi.org/10.1007/BF01586059
  • Stadtler, H. (2010). Multi-level single machine lot-sizing and scheduling with zero lead times. European Journal of Operational Research, 209(3), 241-252. http://dx.doi.org/10.1016/j.ejor.2010.09.022
    » http://dx.doi.org/10.1016/j.ejor.2010.09.022
  • Stadtler, H., & Sahling, F. (2012). A lot-sizing and scheduling model for multi-stage flow lines with zero lead times. European Journal of Operational Research, 225(3), 404-419. http://dx.doi.org/10.1016/j.ejor.2012.10.011
    » http://dx.doi.org/10.1016/j.ejor.2012.10.011
  • Tavares, L. V. (2002). A review of the contribution of operational research of project management. European Journal of Operational Research, 136(1), 1-18. http://dx.doi.org/10.1016/S0377-2217(01)00097-2
    » http://dx.doi.org/10.1016/S0377-2217(01)00097-2
  • Toledo, C. F., França, P. M., Morabito, R., & Kimms, A. (2007). Um modelo de otimização para o problema integrado de dimensionamento de lotes e programação da produção em fábricas de refrigerantes. Pesquisa Operacional, 27(1), 155-186. http://dx.doi.org/10.1590/S0101-74382007000100009
    » http://dx.doi.org/10.1590/S0101-74382007000100009
  • Toso, E. A. V., & Morabito, R. (2005). Otimização no dimensionamento e sequenciamento de lotes de produção: estudo de caso numa fábrica de rações. Gestão & Produção, 12(2), 203-217. http://dx.doi.org/10.1590/S0104-530X2005000200006
    » http://dx.doi.org/10.1590/S0104-530X2005000200006
  • Toso, E. A., Morabito, R., & Clark, A. R. (2009). Lot sizing and sequencing optimization at an animal-feed plant. Computers & Industrial Engineering, 57(3), 813-821. http://dx.doi.org/10.1016/j.cie.2009.02.011
    » http://dx.doi.org/10.1016/j.cie.2009.02.011
  • Unlu, Y., & Mason, S. J. (2010). Evaluation of mixed integer programming formulations for non-preemptive parallel machine scheduling problems. Computers & Industrial Engineering, 58(4), 785-800. http://dx.doi.org/10.1016/j.cie.2010.02.012
    » http://dx.doi.org/10.1016/j.cie.2010.02.012
  • Wolsey, L. A. (2008). Mixed integer programming. In W. W. Benjamin (Ed.). Wiley Encyclopedia of Computer Science and Engineering (pp. 1-10). New York: John Wiley & Sons, Inc.
  • Yamashita, D. S., & Morabito, R. (2007). Um algoritmo exato para o problema de programação de projetos com custo de disponibilidade de recursos e múltiplos modos. Pesquisa Operacional, 27(1), 27-49.

Publication Dates

  • Publication in this collection
    Jan-Mar 2016